Timeline

Pre-Construction

9/10/2012 - Sign purchase agreement with Ryan homes + $5,000 deposit 
9/10/2012 - Structural Options Locked in to expedite the process
9/15/2012 - Meet with NVR Mortgage Rep/Apply for Mortgage
9/22/2012 - Exterior Selections Meeting
9/24/2012 - Huge Deposit paid to Ryan Homes
9/24/2012 - Pre-Construction Meeting

Construction
10/14/2012- Foundation Walls Poured.
10/17/2012 - Waterproofing and Back-Filling of Foundation
10/19/12 - Basement floor and garage slab poured
10/26/12 - Framing Begins
10/29/12 - Framing Complete, roof construction, installation of windows & exterior doors.
10/31/12 - Roof complete, installation of HVAC & plumbing begins.
11/05/12 - Electrical work begins.
11/05/12 - Locked interest rate @ 3.5%
TBD - Pre-Dywall Meeting.
TBD - Siding complete and septic system and well installed.
TBD - Drywall Complete
TBD - Cabinets and Trim Installed
TBD - Appraisal received.
TBD - Lighting, kitchen floors and upstairs bathroom tile installed.
TBD- Hardwood floors installed, electric and plumbing working.
TBD - Driveway, carpet.  Settlement date set.
TBD - Landscaping done and all appliances in.

Post-Construction
TBD - Pre-Settlement Walk-Through
12/27/2012 - Settlement

2 comments:

  1. I am so jealous! You seem to be rocking and rolling and I'm waiting and waiting :)

    ReplyDelete
  2. Our SR said we are setting a record with our timeline, haha - we are living with my parents while we build so we are in a hurry!

    ReplyDelete